email from Herb Nett to CalVal group, 02 Jul 02
... we are indeed somewhat behind the original (pre-launch)
schedule with regard to specific calibration measurements IF1 ... IF16.
This was mainly due to a few 'payload switch-off' events (PLSOL) during
May & June and due to some data recovery and dissemination problems
in the past. See also earlier e-mail to mict on 11 June.
Good news are
- MIPAS has been continously in measurement mode since last PLSOL recovery
on 15 June
- Mission planning activities are progressing well and we hope to
complete most of the IF measurements by around mid next week (10 July).
In particular it seems that the -critical- non-linearity measurement (IF4)
has finally been successful (!!) after several attempts. Acquisition
took place in orbits 1609-1668, 21 - 25 June
- The most recent of several patches in the MIPAS ground processor s/w was
successfully installed in Kiruna on 28 June.
Since 29 June we have routine processing of MIPAS L1B (+ partly L2) data
in the PDS.
The slightly less good news is that today I cannot confirm a date for the
start of data distribution to the CalVal teams.
In summary, we plan stable operation of MIPAS in its nominal measurement
scenario from approx. 11 July onwards and for the duration of the first
correlative campaigns.